Question#11Topic1
You are the project manager of GHT project. Your project team is in the process of identifying project risks on your current project. The team has the option to use all of the following tools and techniques to diagram some of these potential risks EXCEPT for which one?
正解と解説を表示
正解
解説
Incorrect Answers:
A, B, C: All these options are diagrammatical techniques used in the Identify risks process.